We’ve done our best to stay positive, but the latest surprises at the library and cultural centre have finally snuffed our optimism.
The contractor’s shoddy workmanship has hit an all time high—or should we say low?
After attempting to install moveable glass walls in the building, it was discovered that the floors are uneven. That discovery led to a test of every floor in the facility, and according to Peter Waterworth, the chief administrative officer for the municipality, there wasn’t a single floor that met the acceptable plus-or-minus five millimetre standard within a 10-metre square.
Not one.
In fact, “there are places where there is a minus-25 and a plus-10 in a square,” he said.
That’s a difference of 35 millimetres in a 10-metre square.
We at the 51 aren’t contractors, but we do know that the fundamental parts of a building—the floors, the walls, the roof, the stairs and the windows—need to be built correctly.
And we also know that somehow, over the course of this renovation and expansion project, there have been issues with all of those fundamental pieces.
Last year the roof came off after a third-party report showed that it was inadequate, as it didn’t have a vapour barrier, and the air barrier that existed wasn’t tied into the walls.
In February, council found out the interior walls had to be ground down because an additional layer of concrete was added to them, despite the fact that they were supposed to be left as finished concrete.
And now—15 months after the original completion date—the floors are uneven, there’s no design for the windows at the back of the building and the riser for the stairs at the front of the building has been improperly installed, so the stairs can’t sit squarely on top.
During the April 8 committee-of-the-whole meeting, Waterworth said those are the major issues with the building, and there are plenty more minor ones.
This news is staggering.
The project is already more than a year late and a million dollars over budget, and earlier this month council approved a capital budget that includes an additional million dollars for the project, bringing the total budget up to $9.5 million.
Of course, the hope is that most, if not all, of that additional money will be reimbursed following the mediation process at the end of the project. But, like the municipality’s director of finance, we’re not holding our breath.
This project has turned into a nightmare for council, the municipality and the community.
We can only hope that once the saga comes to an end and the building opens, the municipality gets what it paid for—a spectacular facility that’s built to last.